Barton Street Improvements- 67th to 66th Terrace



Project Description:

Mill and overlay, addition of curb and sidewalk, storm sewer, ADA ramps and pavment markings.



Last Updated:
06/21/2017

Capital Improvement

Project Category:
Street Improvements

Project Contact:
Paul Lindstrom, P.E., (913)742-6234

Design Firm:
Walter P. Moore Engineering

Construction Contract:
TBD

Inspection Firm:
Walter P. Moore

Project Status:
Design

Project Number:
3428

Project Start Date:
08/01/2017

Estimated Project End Date:
09/01/2017


Status Details:

Consultant is complete with final plans. A neighborhood meeting was held on 6-15-17. FInal plans will go to the June 26th City Council for approval. Construction to begin late July and be complete within 30 days of notice to proceed. A copy of the final plans is attached.




Notices:


Images:
Barton Street_Final Plan_052417.pdfBarton Street_Final Plan_052417.pdf