Stump Park Trail Streambank Stabilization



Project Description:

Erosion of the channel bank upstream of the pedestrian bridge in Stump Park undermined the existing recreational trail and the trail had to be relocated away from the channel in order to remain in service.

The scope of the project includes stabilization of the north and south banks of the channel for approximately 400 feet upstream of the pedestrian bridge.



Last Updated:
05/02/2017

Capital Improvement

Project Category:
Drainage Improvements

Project Contact:
Bert Schnettgoecke, P.E.,(913)742-6271

Design Firm:
TranSystems

Construction Contract:
To be determined

Inspection Firm:
TranSystems

Project Status:
Design

Project Number:
3417

Project Start Date:
07/15/2017

Estimated Project End Date:
10/15/2017


Status Details:

Final plans have been completed and will be placed on the City Council agenda for approval on May 8, 2017.